Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, June 06, 2007

Dental School :

  • Zimmer continues with the major remediation cleaning on the 5th, 6th, and 7th floors of the Clinic Building.  
    • The 8th floor of the Clinic Building is still in the pre-cleaning stage.
      • The major cleaning is still on going on the 2nd floor of the Administration Building.
  • A & A has moved over to the Administration Building and are finished with the 3rd floor core drilling. 
    • They may be able to start on the 2nd floor tomorrow. 
    • They are unable to work on the upper floors of the Clinic Building while the remediation is continuing.
  • Landis has completed the 2nd floor Clinic area ceiling grid installation. 
    • Light fixtures and ceiling tiles are now being installed on the larger side of the 2nd floor.
    • Firetrol continues to add and relocate sprinkler heads in Clinic building.
  • Boe-Tel continued pulling network wiring on the 2nd, 3rd, and 4th floors in the Clinic Building. 
  • Schindler continues working in the elevator pits of the Administration Building .

1542 Tulane Ave.:

  • Ordes Electrical is pulling additional cable to the new transformers in the vault.
  • Stratos Elevator is still working to complete the installation of the safety brakes on Elevator #3.
  • Arc Mechanical continues the process of installing the new heating hot water pumps in the basement engine room.