Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, August 2, 2007

Dental School

  • Ceiling Installation
    • Landis continues to make progress on punch list items.
    • 1st floor demo and light installation continues
  • Sterilizer Installation
    • Door frames are being installed and sheetrock is being finished
  • Carpet Installation
    • Continues in the library
  • Remediation
    • Awaiting re-samples in Auditoriums A & B.
    • Viable sample results came back and air handlers 7A & 7C passed as well as 4A & 4C in the admin building.
  • IT / Network Closets
    • Light installation and final buildout continues in the Clinic building.
  • Misc.
    • Damaged curbing in the parking lot was removed.
    • AV island in Auditorium C demo was completed with the removal of the fan coil unit and repositioning of the electrical service.
1542 Tulane
  • Conduit has been run underneath the drive over to the parking booth in the L&M lot at the Medical School Building. The pavers have been replaced and the concrete is being replaced.
  • Stratos continues to remove the safeties on the #2 elevator and work on the controls for the #7 and #8 elevators.
Landscaping Project
  • Continued installing wire for irrigation valves around Allied Health and MEB.