Louisiana State University Health Sciences Center Administration & Finance
 

Friday, August 10, 2007

Dental School :

  • Landis has indicated that they have completed all of the Phase 4 punch list items and they are ready for the architects to re-inspect the buildings.
  • Zimmer has removed about half of the old duct work on the 1st floor and will complete the demolition this evening.
  • New walls are being erected in area 3, 1st floor of the Clinic Building . 
    • Lights have been installed in area 2.
    • The new ductwork installation continues.
  • The installation of electrical outlets and fixtures in the Central Sterilization continues. 
    • The floor is being prepped in the area where the new sterilizers are to be installed.
  • Carpet installation will begin in Auditorium C next week.
  • The installation of the 1st floor stairwell fire doors is complete.
    • The doors and frames have been painted.

1542 Tulane Ave. :

  • Stratos continues to work on Elevator #2 installing new travel cables.
  • Siemens completed the removal of the obsolete fire alarm devices up through the 8th floor.

MEB Duct Cleaning:

  • The ducts on the 3rd floor are now completed after one area was re-cleaned.
  • The 2nd floor Maintenance areas were cleaned last night.
  • Cleaning of the 2nd floor ducts will continue this evening.