Dental School:

  • Landis is preparing to level the floor in areas 1 and 2 on the 1st floor of the Clinic Building.
    • The final connections to the temporary AHUs are being made this week.
    • The walls in the elevator lobby are being taped and floated and will be ready for paint tomorrow. 
    • Work on the temporary doors to areas 1 and 2 will begin tomorrow.
  • Both of the sterilizers were moved into their final positions in the Central Sterilization area.
    • Floor leveling started in the rest of the area this morning. 
  • The installation of carpet in Auditorium C is nearly complete.

MEB Duct Cleaning:

  • Duct cleaning continued on the 5th floor over the weekend and the contractor will finish up tonight. 
  • Cleaning will begin on the 6th floor tomorrow.  Personal notifications were made on the 6th floor informing faculty and staff of the scheduled work.

1542 Tulane Ave.:

  • Ordes was making a list of materials needed to provide power to the gate operators at the L & M Lot, Lakeside Lot, & the 1542 Garage.
  • Stratos Elevator Co. is installing the tape selector and the TLS box which controls the elevator leveling for Elevator #2.
  • Siemens continues to work on the fire alarm system; installing a new riser for the fire alarm wiring.

Landscaping Project:

  • The crews cleaned and graded the new planting beds on the S. Prieur St. side of the Lions/LSU Clinic Building. 
  • Four new Savannah holly trees were planted on the S. Prieur St. side of the Lions/LSU Clinic Building.