Tuesday, August 21, 2007 Dental School :
- Electrical connections to outlets and switches are being made in the temporary spaces being constructed on the 1st floor of the Clinic Building .
- The build out of the walls is nearly complete.
- The connections to the air handling units are being made.
- The floor leveling in the Central Sterilization area is complete and the floors are ready for the vinyl covering.
- The carpeting of Auditorium C has been completed.
- The installation of carpet in the Deans Office has begun.
- The installation of replacement light poles around the grounds is nearly complete.
MEB
Duct Cleaning:
- The cleaning of the 5th floor ducts is complete.
- The cleaning of the 6th floor ducts begins this evening.
Landscaping
Project:
- The crews continued planting on the S. Prieur St. side of the Lions/LSU Clinic Building.
|