Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, August 28, 2007

Dental School :

  • Electrical wiring continues to be run throughout area 3 on the 1st floor of the Clinic Building.
    • The construction of the mechanical room in area 3 is nearly complete.
    • Electrical equipment is being installed.
    • The fur down in the elevator lobby is roughed-in. 
    • A temporary door in area 1 has been installed.
  • Carpet continues to be installed on the 2nd floor of the Administration Building.
  • Getinge continues to install the remaining equipment in the Central Sterilization room.
  • The replacement of the old acid waste drain pipe is progressing, with some new sections being installed on the 1st floor of the Clinic Building .

MEB Duct Cleaning:

  • Work continues on the 7th floor.
  • The contractor expects to finish the project Thursday night.

1542 Tulane Ave. :

  • Stratos Elevator delivered the cabs for Elevators #7 & #8 and continues to work on Elevator #2.
  • Siemens continues working on the fire alarm system, adding junction boxes on each floor in the new fire alarm riser.

Landscaping Project:

  • The crews completed the installation of the remaining bushes on the S. Prieur St. side of the Lions/LSU Clinic Building.  This completes the landscaping around this building.
  • Crews also worked on preparing trenches on Bolivar St. side of the MEB and the Allied Health/Nursing Building to run the wire for controlling the irrigation system.