Wedesday, September 5, 2007
Dental School:
- 1st Floor
- Floor is being leveled in area 2.
- Electrical is being run in main lobby and fixtures arrived today for installation.
- Area 3 mechanical room connections are being made.
- Furdown in main lobby continues to be installed.
- Sterilizer
- Landis is completing wainscoting and final paint today.
- Door hardware and trim is being installed.
- Getinge continues to connect equipment.
1542 Tulane Ave :
- Stratos Elevator Co. is wiring the car operator panel, the top of the elevator car & the controller for elevator #2. Also, Stratos delivered additional materials (wiring, conduit, & wiring duct) to the site for the controllers of elevators #7 & #8.
- Arc Mechanical is on site labeling the insulated chilled water supply & return lines.
- American Sprinkler Co is on site replacing two leaking valves on the fire pump that were corroded by the flood waters.
- Siemens continues to install fire alarm device boxes on the 1st floor.
|