Wednesday, September 12, 2007
Dental School :
- 1st Floor
- Build out continues with light fixture installation and wall finishing.
- Sterilizer
- Installation is nearly complete and Getinge is waiting for electrical drop to be installed.
- Miscellaneous
- Site lighting project is progressing.
- Asbestos survey for barracks to be demolished was completed. Sample results and demolition plan is expected soon.
1542 Tulane Avenue :
- Ordes continues to install new control wiring.
- Arc Mechanical completed the construction of the wooden form for the generator foundation and is scheduled to begin pouring the concrete on tomorrow, weather permitting.
- Stratos Elevator Co. continues to wire the control panel for elevator #2.
- Siemens continues to work on the installation of fire alarm device boxes on the 3rd floor.
Landscaping Update:
- Completed the removal of the dead vegetation on the Gravier Street side of Allied Health and Nursing.
|