Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, September 19, 2007

Dental School :

  • The wall framing in the Clinic Building main lobby area is nearly complete.
    • The lighting and electrical switches have been installed.
    • Area 3 mechanical room controls are being installed.
  • Getinge has completed the installation of the remaining sterilization equipment in the Central Sterilization unit and the punch-list items are being resolved by Landis.
  • The process of removing old HVAC inline zone dampers and installing new ones is proceeding throughout the buildings.

1542 Tulane Ave. :

  • Ordes set the temporary emergency generator on the new concrete foundation and they have begun to make the connections to the building.
  • Stratos Elevator continues to make the final adjustments to Elevator #2.
    • They are also installing new wiring for the controller for Elevator #8.
  • Siemens is installing fire alarm device boxes on Floors 7 and 8.

Landscaping Project

  • The trenching for the irrigation sprinkler piping on the Gravier St. side of the Allied Health/Nursing building is substantially complete.
  • Crews completed the installation of the irrigation valves around the MEB.
    • They started installing the irrigation valves and sprinkler piping on the Gravier St. side of the Allied Health/Nursing Building.