Louisiana State University Health Sciences Center Administration & Finance
 

Monday, September 24, 2007

Dental School :

  • The installation of new sheet rock in the 1st floor lobby of the Clinic Building is nearing completion. 
    • Work in the mechanical room in area 3 is complete and equipment testing has begun.
    • Electrical circuits continue to be connected throughout the 1st floor.
  • The change order to add an air line and reposition the sterilizer shutoff valves in the Central Sterilization unit has been given to Landis for execution.
    • Siemens has been issued a PO to sanitize and flush the reverse osmosis water system.

1542 Tulane Ave. :

  • Ordes continues to install conduit to the temporary emergency generator. 
    • They are also connecting the generator's internal control wiring.
  • Stratos Elevator Co. continues to wire the controllers for Elevators #7 and #8 to run on inspection mode.
  • Siemens is installing conduit to all of the fire alarm device boxes in the basement.

Campus Elevator Upgrades:

  • MEB elevator #1 was certified for operation with the new electronic controller.