Tuesday, September 25, 2007 Dental
School - The
sheet rock installation on the reception walls in the lobby of the Clinic
Building is complete.
- Lighting
installation has begun.
- The
mechanical room systems continue to be checked out and are nearly ready to be
brought on-line.
- Landis
is working on the air line installation and valve repositioning in Central
Sterilization
- Doors
for the new network/telecom closets should be arriving this week and the final
build out will occur once they arrive.
1542
Tulane Ave.:
- Ordes
Electric completed the conduit installation for the emergency generator.
- Arc
Mechanical is replacing the pressure gauges on the Energy Transfer Station and
is making a materials list for the installation of the pre-cooler for the main
air compressor
- Stratos
Elevator continues to work on getting Elevators #7 and #8 to run in inspection
mode.
- Siemens
continues to install conduit to the fire alarm device boxes in the basement.
|