Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, September 27, 2007

Dental School:

  • The installation of new ceiling grid in the Clinic Building 1st floor elevator lobby has begun. 
    • The walls are complete and being prepped for painting.
    • The ceiling light fixtures are installed and Landis is waiting for the final painting to be completed to install trim.
  • The mechanical room is complete and all of the controls have been installed  
  • The air handler in area 1 is operational.
  • Landis is awaiting final change order paperwork to begin work on the valve repositioning and additional air line installation in the Central Sterilization unit.
    • Siemens will begin decontaminating the RO system next week.
  • Site lighting installation and replacement is complete and awaiting connection of power by Entergy.

1542 Tulane Ave.:

  • Ordes installed 110V circuits from emergency panel EPL1 to the emergency generator for the battery charger and other miscellaneous generator power requirements.
  • Stratos Elevator is replacing the door guides on Elevator #2 and continues to remove the buffers on Elevator #8.
  • Siemens continues to work on the fire alarm system.

Landscaping Project:

  • The crews completed the installation of irrigation stations 4, 5 & 6 for the Allied Health/Nursing Building at the corner of Gravier St. and Bolivar St. and along the Bolivar St. side of Allied Health/Nursing. 
  • Completed the wiring between the junction box for irrigation valve wires and the irrigation controller.

Sidewalk Project:

  • Boh Brothers has completed the sidewalk project.