Louisiana State University Health Sciences Center Administration & Finance
 

Monday, October 01, 2007

Dental School:

  • The ceiling grid is completely installed on the lobby of the 1st floor of the Clinic Building.
    •  Landis is awaiting the materials for the curved ceiling that will be installed in the main lobby and into the elevator lobby.
  •  Landis began the electrical trim out of the lights; installing fixtures and bulbs in the Clinic Building elevator lobby. 
  • The installation of the supply grilles and return grilles for the HVAC continues around the 1st floor spaces.
  • The wall clad granite and the storefront windows are being cleaned in the Clinic Bldg.
  • The painters are completing the last of the punch list items in the Central Sterilization area.
  • Siemens continues their work on AHU 1-1; installing safety devices and thermostats.
  •  A-1 Signs started work on the LSU School of Dentistry sign.
    • They are trouble shooting the power for the neon lights that illuminates the sign and they are painting the existing letters.
  • Schindler continues to work on repairing the freight elevator. 
    • They are currently installing the additional safety breaks and wiring the new electronic controller.
1542 Tulane Ave.:
  • Ordes installed the emergency generator power wiring between the generator and the ATS. They will begin terminating the wires tomorrow. 
  • Stratos Elevator is installing new wiring for the motors of Elevators #7 and #8.\
    • They are also installing and programming new position sensors for Elevator #2.
  •  Siemens continues with the fire alarm system installation.

 
Landscaping Project:

  • The crews finished installing 3" conduit and routing irrigation valve control wires into the first floor of MEB to the controller. 
    • They have completed making the control wire connections for stations 1 through 6.