Wednesday, October 03, 2007 Dental
School:
- All
of the lights have been installed in the Clinic Building 1st floor lobbies
except for the indirect lights that will be located on top of the fur downs.
- Siemens
continues to run wire for the controls of the HVAC system that will serve the
1st Floor of the Clinic Building.
- The
repairs to the LSU School of Dentistry sign are complete. The missing “L†has been installed and all of the back lighting has
been repaired.
- Schindler
continues to work on repairing the controls for the freight elevator and installing
the alarm bells for Elevators #6 and #7.
- The
sanitization of the reverse osmosis system began today and should be completed
by the end of the week.
- The
bid for the permanent repairs to the roofs of the main Dental School campus
buildings will be advertised this week.
An expedited bid period will be used to help move the project forward as
quickly as possible.
Landscaping
Project:
- The
crews installed the nozzles on sprinklers located on stations 4 & 5.
- Stations
4 & 5 were programmed to operate automatically on the
controller.
- The
planting has begun on the Gravier St. side of the Allied Health/Nursing
Building.
- New
trees have been planted.
- Crews
also began installing bushes/shrubs in the planting beds along the Gravier St.
side of both the MEB and the Allied Health/Nursing Building.
|