Monday,
November 12, 2007 1542 Tulane Ave. :
- Siemens is on site installing fire alarm speakers and strobes on Floors 9 and 10.
- The painting contractor is floating the walls in Stairwell B on Floors 1 - 3.
- The contractor is removing the peeling paint in Stairwell A on Floors 1 - 8.
Dental School :
- The temporary wall separating the 1st Floor lobby spaces in the Clinic Building has been removed.
- The reception desk is now installed completing the lobby furniture.
- The contractor is awaiting the material to wrap the columns behind the curved wall and two light fixtures that will hang through the curvature ceiling.
- Intrepid Stone began replacing the stone pavers on the walk way near the side entrance to the Clinic Building and on the Moss Street side of the Admin Building .
|