Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, November 21, 2007

1542 Tulane Ave. :

  • Stratos Elevator continues their work on Elevators #7 and #8.
    • They finished removing the platform and cab walls in Elevator #7.
    • The contractor installed new rollers on Elevator #8.
  • Zimmer-Eschette continues to work on Floors 1 and 8 removing building debris.
    • The contractor is also cleaning the ducts on the 1st floor and preparing for the duct cleaning on the 8th floor.

Dental School :

  • Landis installed a ceiling access panel for the drywall ceiling in the Clinic Building lobby and continued to touch-up the sheetrock walls, fur downs, and ceilings.
    • Verges-Rome Architects was on site inspecting the completed work.
  • Landis re-finished the walls of the 2nd Floor Administration Building Conference Room; sanding and painting the spots that required touch-up.
    • The flooring contractor began installing the new cove base.

Landscaping Project:

  • All of the new plants have been installed on the S. Roman St. side of the Allied Health/Nursing Building.