Louisiana State University Health Sciences Center Administration & Finance
 

Monday, November 05, 2007

1542 Tulane Ave. :

  • Ordes Electric continues the installation of the PLC which monitors and controls the Energy Transfer Station. 
  • Siemens is installing the new fire alarm system wiring, speakers, and strobes on the 6th Floor. 
  • The painting contractor continues to float the walls on Floors 1 and 2 of Stairwell D.
    • The contractor also continues to sand the floated on Floors 3 - 7. 
  • Faculty members and staff continue to clean out their offices and remove personal items on Floors 5 and 6 in preparation for the final remediation, duct cleaning and painting. 
  • The steam lines continue to be checked and monitored for proper operation.

Dental School :

  • The installation of the Curvature ceiling in the 1st Floor lobby continues. 
    • The Barrel ceiling installation is complete. 
  • The installation of the new duct work in the 2nd Floor conference room in the Administration Building is complete.
    • The initial finish coat of paint has been applied to the walls. 

Landscaping Project:

  • Irrigation Stations #23 & #24 on the Bolivar St. side of the MEB have been activated. 
    • Crews installed plants and mulch on the Bolivar St. side the building.