Wednesday, January 16, 2008 1542 Tulane
Ave.:
- Siemens
finished trouble-shooting the fire alarm wiring in the basement, 8th Floor, and
the mechanical and animal care spaces on the roof.
- The
contractor is pulling the main fire alarm communication trunk/riser through the
pipe chase from the 1st Floor to the 8th Floor.
- Stratos
Elevator continues to install the buffers for Elevator #8.
- They
are also installing new door hangers for Elevator #1.
- ATT/Bell
continues to work on relocating the telephone demark to the 2nd Floor in Room
243.
- Zimmer-Eschette
is encapsulating the ducts on the 5th Floor.
- Zimmer
completed the removal of floor tile on the 6th Floor and has started working on
the tile removal on the 4th Floor.
- The
painting contractor continues to float the walls in Suite 123 and Room 866.
- The
contractor continues to paint the walls on the 8th floor.
- Trison
Constructors finished installing sheetrock for the new network closet in Room
356, 357, and 357A.
- Sample
Results:
- The
6th floor passed TEM clearance for asbestos floor tile removal.
- The
5th floor passed clearance for mold testing, except for rooms 550, 531, 556
and 557.
Dental School :
- Sherlock has most of the new walls for the temporary bookstore framed and sheet rocked.
- They have installed the duct board and flex duct for the supply air and return air to the temporary bookstore area as well as the existing adjacent rooms.
- Trison Constructors completed the demolition of the existing oven duct work and began the installation of the new ducts in the basement and on the 1st Floor.
- Needham Roofing removed approximately one half of the penthouse roof on the Clinic Building and removed most of the debris from the roof.
- Securitas ran coax cables for the intercom system to the front desk located in the Clinic Building , 1st Floor lobby.
Landscaping Project:
- Two additional irrigation stations have been completed on the Perdido St. side of the MEB yesterday.
- Weather prevented crews from working today.
|