Friday, February 01, 2008 1542 Tulane
Ave.:
- Stratos Elevator is installing the elevator cab roof for Elevator #1.
- They finished installing the rope gripper for Elevator #8.
- The remediation contractor continues to seal the HVAC ducts on the 4th Floor.
- Zimmer continues to remove building debris from the rear portion of the building.
- Zimmer finished the final cleaning on the 2nd Floor in the offices along the main corridor.
- The 2nd floor passed visual inspection and air samples were taken.
- The contractor finished painting in Suite 123 and is prepping the walls in Suite 122 .
- The contractor continues to prime the walls on the 7th Floor and is floating the walls on the 5th Floor.
- Trison Contructors finished the flooring installation for the 1st and 3rd Floor network closets.
- The contractor finished painting the network closet on the 3rd floor.
Dental School :
- Needham Roofing removed the unneeded roofing material from the Clinic Building.
- They began to remove the old roof from the west side of the Administration Building .
- The 1st ply of the new roofing material has been installed over the section where the old roofing was removed.
- Schindler installed the purple wall panels, ceiling and lights in Elevators #3 and #4.
|