Tuesday, April 22, 2008 1542 Tulane Ave.:
- Zimmer-Eschette continues to prepare the 1st Floor side entrance and corridor in the old section of the building for remediation cleaning.
- The painting contractor is prepping the walls and the rear stairwell on the 8th Floor in the old section of the building.
- Royerre Commercial Carpet continues to install cove base and transition strips on the 3rd Floor.
- Trison Construction is installing the flooring for the 4th Floor network closet.
- The Herman-Miller group continues assembling and installing furniture in the offices on the 5th Floor.
Dental School :
- Needham Roofing completed work on the replacement of the Power Plant roof.
- They began loading material onto the Clinic Building roof to resume the work on the roof of the penthouse.
|