Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, April 23, 2008

1542 Tulane Ave. :

  • Zimmer-Eschette continues to prepare the 1st Floor side entrance and corridor in the old section of the building for the final remediation and cleaning.
  • The painting contractor is prepping the stairwells along Tulane Ave.
  • Royerre Commercial Carpet continues to install cove base and transition strips on the 3rd Floor.
    • Their crews have begun to install cove base and carpet tiles on the 2nd Floor.
  • Trison Construction finished installing the flooring in the network closet on the 4th Floor.
    • The contractor finished installing the additional electrical outlets in the same network closet.
  • The Herman-Miller group continues assembling and installing furniture in the offices on the 5th Floor.
  • Hogues continues to install the new ceiling light fixtures on the 3rd and 4th Floors.

Lions/LSU Clinic Permanent Repairs and Mitigation:

  • CMI continues to frame the new interior walls on the 6th Floor.
  • The installation of the rough in plumbing and electrical service on the 7th Floor in the new laboratory space continues. 
  • The crews continue to clean the remaining 1st Floor windows and applying the anti-corrosion coating to the metal window frames.

Dental School :

  • Needham Roofing resumed work on the Clinic penthouse roof. 
    • They removed a 20 square section of material that was damaged from water intrusion and installed new insulation, decking and the granulated cap sheet.

Exterior Lighting Project:

  • Frischhertz is painting the bases of the new light poles that have been installed at the Residence Hall parking lot.