Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, April 24, 2008

1542 Tulane Ave. :

  • Stratos is changing out the components in the elevator pit for Elevator #7.
  • The painting contractor is painting the stairwells along the Tulane Ave. side of the building.
    • The contractor is prepping Stairwell D in the old section of the building.
  • Royerre Commercial Carpet continues to install cove base and transition strips on the 3rd Floor.
    • Their crews continue to install cove base and carpet tiles on the 2nd Floor.
  • The Herman-Miller group continues the process of assembling and installing furniture in the offices on the 5th Floor.
  • Hogues continues to install the new ceiling light fixtures on the 3rd and 4th Floors.

MEB Roof Replacement:

  • Crawford Roofing continues to apply the final layer of roofing material on the main roof of the building.

Exterior Lighting Project:

  • Frischhertz crews are painting the bases of the new light poles that were installed at the Residence Hall.

Lions/LSU Clinic Permanent Repairs and Mitigation:

  • CMI continues to frame the interior walls on the 6th Floor for the new Cohn Learning Center .
  • The rough in plumbing and electrical installation in the laboratory space on the 7th Floor is progressing well.