1542 Tulane Ave. :

  • Stratos continues to install elevator components in the elevator pit for Elevator #7.
    • The contractor is removing trash and debris from the jobsite.
  • Zimmer-Eschette began cleaning the offices near the side entrance on the 1st Floor.
  • The painting contractor finished painting the stairwell along Tulane Ave. on the I-10 side of the building and Stairwell D in the old section of the building.
    • Painters began painting the middle stairwell along Tulane Ave. (Stairwell C).
  • Royerre Commercial Carpet continues to install cove base and transition strips on the 2nd and 3rd Floors.
  • Hogues continues to install the new ceiling lights on the 3rd and 4th Floors.

Lions/LSU Clinic Permanent Repairs and Mitigation:

  • CMI continues to frame up the interior walls on the 6th Floor and install the rough in plumbing and electrical on the 7th Floor. 

Parking Lot Improvements:

  • Boh Bros formed and poured the concrete curb and driving lane for the I-10 Lot #3.
    • The contractor connected and installed the new culvert to the underground drainage.

Dental School :

  • Needham Roofing replaced 38 squares of insulation and decking material on the Clinic Building penthouse roof. 
    • They installed new insulation, decking, granulated cap sheet, and perimeter flashing.