1542 Tulane Ave. :

  • Zimmer-Eschette continues cleaning the corridor and offices near the side entrance on the 1st Floor.
  • The painting contractor continues to paint the middle stairwell along Tulane Ave. (Stairwell C).
  • Royerre Commercial Carpet continues to install cove base and transition strips on the 2nd and 3rd Floors.
  • Boe-Tel is connecting the new fiber optic cable on the 3rd Floor.
  • Hogues continues to install the new ceiling light fixtures on the 3rd and 4th Floors.

Lions/LSU Clinic Permanent Repairs and Mitigation:

  • CMI continues to frame the new interior walls on the 6th Floor and install the rough in plumbing and electrical on the 7th Floor. 
  • Crews are cleaning the 1st Floor windows and applying anti corrosion coating to the metal frames of the windows.