Wednesday, April 30, 2008 1542 Tulane
Ave.: - Stratos
is working to restore power to Elevator #4 and is cleaning the rails in the elevator
shaft.
- Zimmer-Eschette
continues to clean the corridor and offices near the side entrance on the 1st Floor.
- The
painting contractor continues prepping the stairwell located along Tulane Ave.
on the Charity side of the building.
- Royerre
Commercial Carpet continues to install cove base and transition strips on the
2nd Floor and has begun installing carpet on the 1st Floor.
- Boe-Tel
finished installing the network rack in the network closet on the 4th Floor and
is preparing the wires for termination on the rack/switch.
- Hogue is removing the old hallway lights from the plaster ceilings so the openings can be modified and patched to receive the new ceiling fixtures.
Dental School :
- Needham Roofing completed the installation of the two ply roof on the Clinic Building penthouse.
- They still need to complete a minimal amount of flashing and metal work.
- Sherlocks Construction pulled wires in preparation for connecting the new transformer and electrical panels.
Lions/LSU Clinic Building Permanent Repairs and Mitigation:
- CMI is working on installing the rough in plumbing, mechanical and electrical on the 6th and 7th Floors.
Downtown Landscaping Project:
- Crews installed the edging around the planting beds and completed all the final grading on the Perdido St. side of the MEB.
- Sprinkler station # 17 on the Perdido St. side of the MEB has been activated.
- This area is now ready to start installing landscape plants.
|