Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, May 1, 2008

Lions/LSU Clinic Permanent Repairs and Mitigation:

  • CMI is working on the mechanical systems on the 2nd, 6th and 7th floors.
  • Their plumbers continue to complete the rough in plumbing on the 6th and 7th Floors.
  • The electricians are roughing in the electrical on 6th and 7th Floors.
  • Crews have started installing sheetrock on the new walls that form the laboratory on the 7th Floor.

1542 Tulane Ave. :

  • Stratos is installing lighting in the shaft for Elevator #7.
  • Zimmer-Eschette finished cleaning the corridor and offices near the side entrance on the 1st floor.
    • The area passed the visual inspection and will be tested.
  • The painting contractor is painting the bathrooms in the rear of the building on the 7th and 8th Floors.
  • Royerre Commercial Carpet continues to install cove base and transition strips on the 1st and 2nd Floors.
  • Boe-Tel is installing the telephone feeder cables for the network closet on the 2nd Floor.

Dental School :   

  • Needham resumed work on the main roof of the Clinic Building . 
    • They tore off and replaced 3 squares of material in order to trace the wet insulation. 
    • They secured temporary seams to prepare for rain that is forecast for Friday and Saturday.

Downtown Landscaping Project:

  • The plantings on the Perdido Street side of the MEB are complete..