Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, May 14, 2008

Lions/LSU Clinic Building Permanent Repair and Mitigation:

  • CMI is installing sheetrock on the new interior walls for the Cohn Learning Center that is being re-built on the 6th Floor.
  • The mechanical sub-contractor continues working on the mechanical systems on the 2nd and 6th Floors.
  • The plumbers are working in the laboratory space on the 7th Floor.
  • The electricians continue their work on the 6th Floor.

1542 Tulane Ave. :

  • Stratos is installing whisper-flex cable for Elevator #7.
  • The contractor finished painting the handrails in Stairwell C (Center Corridor).
  • Royerre Commercial Carpet is installing carpet tiles in offices on the 2nd Floor along the center corridor.
  • Trison finished sealing the ceiling holes in the main corridor on Floors 2 and 3.
    • They are installing ceiling tiles in the patched areas.

Dental School :

  • Needham Roofing completed the installation of the granulated cap sheet on the main roof of the Clinic Building and crews continue to complete the associated metal work. 
    • They completed the re-caulking of the parapet wall on the perimeter of the Clinic Building roof.
  • Alfortish Enterprises has completed sandblasting the black stone pavers on the north and east sides of the Clinic Building. 
  • Schindler ran conduit for the car operator and installed the cables for the hoist way on Elevator #2 in the Clinic Building .

Parking Lot Lighting:

  • Frischhertz is working on the punch list for the all of the parking lots where new lighting has been installed.