Friday, May 23, 2008 Lions/LSU
Clinic Building Permanent Repairs and Mitigation:
- Construction Masters is working on the plumbing, electrical and mechanical systems in the new Cohn Learning Center .
- Crews are installing sheetrock on the interior walls throughout the 6th Floor.
1542 Tulane Ave. :
- Stratos is installing and mounting components on the top of the cab for Elevator #7.
- The contractor is changing the rollers for Elevator #7.
MEB
Roof Replacement:
- Crawford continues to work on the metal trim and cap sheet on the parapet walls that run around the perimeter of the roof.
|