Wednesday, June 11, 2008

1542 Tulane Ave.:

  • Stratos finished changing the travel cables for Elevator #7.
    • The technicians are changing the governor sheave and governor ropes.
  • The contractor is painting the ceiling in the Tulane Ave. entrance lobby on the 1st Floor.
  • Zimmer-Eschette is priming and painting the mechanical room walls on the 6th and 7th Floors.
  • Premier Source Inc. continued detailing the terrazzo and ceramic base on the 8th Floor.
  • Brooks Window Coverings finished installing the mini-blinds on the 3rd and 4th Floors.
    • Crews began installing new mini-blinds on the 1st and 2nd Floors.

Residence Hall Lobby Renovations:

  • Zimmer continues the removal of the old flooring from the lobby.  They are working toward the A Tower elevator.
  • The concrete pad is being built for the new air handling unit. 

MEB MDL Lab #5 Renovation:

  • AEC is removing the old floor tile from MDL #5 and is prepping for tile removal in selected Pharmacology areas.

MEB Lecture Rooms A & B Enhancements:

  • Trison is completing the installation of new electrical conduits in Lecture Room A and continue to work in B. 
  • The new floor ducts are on order.

Dental School : 

  • Premier Source Inc. completed honing the terrazzo floors in the Clinic Building 2nd Floor lobby and waiting area. 
    • Work continued within the same area on the 3rd Floor. 
    • Work began in the area between the elevators on the 4th Floor.

Lions/LSU Clinic Building Permanent Repairs and Mitigation:

  • The removal of the ground level slab from the front of the building continues. 
  • Dry flood-proofing of the pit for Elevators #2 and #3 pits is progressing.
  • Electrical work and sheetrock work continues on the 2nd Floor. 
  • Plumbing, mechanical, electrical, sheetrock, and fire sprinkler work continues on the 6th Floor. 
  • The gas line continues to be installed on the 7th Floor for the new lab.

MEB 2nd Floor Lobby Renovation:

  • Zimmer removed the floor tile from in front of Campus Office Stores, the Mens Room, the stairwell closest to the elevated walkway to the Residence Hall, and the Planning Office.