Louisiana State University Health Sciences Center Administration & Finance
 

Monday, June 16, 2008

1542 Tulane Ave .:

  • Stratos finished changing the governor sheave and governor ropes on Elevator #7.
    • The technicians continue to wire the car station.
  • Hogue & Associates finished removing the old ceiling light fixtures in the old section of the building near the near the rear elevators on all floors.

Lions/LSU Clinic Building Permanent Repairs and Mitigation:

  • CMI is preparing the slab and front façade for the steel required for the new exterior stairwell on the front of the building.
  • Dry flood-proofing of the pit for Elevator #2 and #3 continues.
  • Electrical work and sheetrock work continues on the 2nd Floor.
  • Plumbing, mechanical, electrical, sheetrock, and fire sprinkler work continues on the 6th Floor.
  • The gas line for the new 7th Floor lab has been installed.

MEB 2nd Floor Lobby Renovations:

  • Zimmer removed the metal from the storefront and fixed the lights in the CAD conference room.

Downtown Landscaping Project:

  • Crews continued installing plants in the Pocket Park in Student Parking Lot # 2.
  • The tree service has agreed to replace the 'Drake' Chinese Elm tree that did not survive being transplanted. 
    • The replacement tree will be container-grown instead of being transplanted.

Dental School :

  • Premier Source completed honing the terrazzo floor on the 4th Floor of the Clinic Building.
    • They are now working on the black terrazzo on the 4th Floor of the Administration Building .