Clinic Permanent Repairs and Mitigation:
The planned shutdown on Saturday went well.
The fire-proof sleeve was installed between the Entergy vault and the switchgear room for service to new switchgear on the 2nd Floor.
1542 Tulane Ave. :
Stratos Elevator continues replacing the hoist cables for Elevator #7.
The contractor continued installing suspended ceilings in several offices, patching and painting offices and working on punch list items.
The mechanical contractor is installing fan coil units in the lounges on Floors 5, 6 and 7.
Plumbers are capping piping and installing segregation/shut off valves.
Roman St. Garage:
The contractor is applying sealant to the 7th Floor.
Downtown
Perimeter Fence Project:
The contractor is constructing concrete forms on the corner of Poydras and Bolivar Streets in Student Lot #2 in preparation for pouring the concrete bases for the decorative fence bases.
Residence
Hall Lobby Expansion:
MCC completed the installation of the ductwork for the AHU on the mezzanine level.
The contractor completed framing and hung dry wall for the new mechanical room.
Residence
Hall Walkway Resurfacing:
The contractor filled the center drains and leveled the area in preparation to receive the material needed to slope the surface.
MEB
MDL #5 Renovations:
The contractor continues to modify the steel support for the new partition track.
Plumbing demolition continues in the main room.
MEB 2nd
Floor Lobby Renovations:
The contractor is grinding the floors to prepare for the installation of the new flooring.
MEB 4th
Floor Ceiling Replacement:
The contractor began framing the fur downs for the Tray ceiling.
Library
Commons:
The work on constructing the bulk head that runs the length of the Commons area continued.
Facility Services electricians continued the electrical rough-in work.
Duct
Cleaning:
Crews completed cleaning the ducts on the 4th Floor of the CSRB.