Louisiana State University Health Sciences Center Administration & Finance
 

Monday, July 7, 2008

1542 Tulane Ave. :

  • The contractor is touching up paint throughout the 7th Floor.
  • Securitas continues to pull new wiring through the new conduit that has been installed for the card readers and cameras on the 1st Floor.
  • Hogue & Associates finished removing ballasts from old light fixtures and disposing of the old fixtures from Floors 4 through 8.
    • Crews began installing new single-faced exit signs on Floors 1 through 6.
  • Premier Source Inc. finished honing the terrazzo on the 4th Floor in the Tulane Ave. corridor and the center corridor.

Downtown Perimeter Fence Project:

  • US Fence & Gate Co removed the chain link fence from Student Lot #2 along Bertrand Street and is replacing it with new 6 ft. vinyl-coated chain link fencing.