Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, July 8, 2008

1542 Tulane Ave. :

  • The contractor continues to touch-up paint in offices on the 7th Floor.
  • Securitas continues to pull wiring through the new conduit that has been installed for the card readers and cameras on the 1st Floor.
    • The contractor has pulled the wiring for devices in the old section of the building and along the center corridor, up to the Tulane Ave. elevator lobby.
  • Hogue & Associates continues to install new single-faced exit signs on Floors 1 through 8.
  • Premier Source Inc. is prepping the 3rd Floor for terrazzo honing.
  • Merit Sprinkler is on site repairing the dry-pipe sprinkler system piping in the parking garage.

Downtown Perimeter Fencing Project:

  • US Fence & Gate Co. removed the chain link fence from Student Lot #3 along Bertrand Street and is replacing it with new 6 ft. vinyl-coated chain link fencing.
  • The contractor has begun removing the chain link fence along Bolivar Street at the Residence Hall Parking Lot and is replacing it with new 6 ft. vinyl-coated chain link fencing.

Dental School :

  • Needham Roofing is sandblasting the roofing tar from the penthouse walls.