Stratos Elevator crews continue to complete repair work on Elevator #4.
The general contractor continues patching walls and painting on the 5th Floor.
Demolition of the 3rd and 4th Floor annex space continues.
The demolition of the existing sidewalk along Tulane Ave. is underway.
The contractor is also working on grading the site and laying out the new sidewalk in front of the building.
The contractor continues dry proofing light well enclosures that have been sealed.
LSUHSC Facility Services continues adjusting fan coil units, installing locksets, working on maintenance items throughout the building, and installing signage.
The lighting contractor continues installing lights on various floors.
The window blind vendor delivered and installed new blinds in various rooms.
They began making punch list repairs.
The Herman Miller Group set-up and arranged new furniture in offices on the 8th Floor in the final layout.
Dental
Campus Roof Replacement:
The roofing contractor continues to work on punch-list items, including caulking and weather-proofing.
Dental School
Auditoriums A&B:
The contractor began removing domestic water connections in the auditoriums.
Dental School
Lab Renovations:
The contractor began removing wall panels on the 8th Floor.
Library
Commons:
LSUHSC Facility Services continues with the electrical rough-in for the Coffee Kiosk.
Lions/LSU
Clinic Permanent Repairs and Mitigation:
The contractor continues installing door frames on the 7th Floor.
The mechanical sub-contractor is piping in the new AHU on the 1st Floor on the S. Prieur St. side of the building.
Crews are demolishing the bathrooms located on the 6th Floor on the Bolivar St. side.
The VAVs on 6th Floor are still being piped in.
The electricians are running copper cable from the Entergy vault to the new switchgear.
MEB
MDL #5 Renovations:
The contractor completed installing the new ceiling grid.
The electrician continues installing light fixtures in the new grid.
MEB 2nd
Floor Lobby Renovations:
The crews are taping and floating the new sheetrock.
MEB 4th
Floor Ceiling Replacement:
Contractor continues working on the installation of the new ceiling grid.
They are approximately forty-five percent complete.
The contractor started taping and floating the new sheetrock ceilings in the student lounge areas.