The new sidewalk in front of the building is complete.
The new concrete was poured and finished over the weekend.
Plumbers capped disconnected plumbing on the 3rd and 4th Floor center hallways.
The work on the restrooms is complete except for floor mounted urinals (1st Floor) and new flush valves (2nd - 4th Floors).
Stratos Elevator continues work on Elevators #4 and #7.
Zimmer continues patching walls and painting on the 5th Floor.
The new walls are being constructed in the 5th and 6th Floor lounges.
The contractor continues the installation of fan coil units.
The insulation contractor continues insulating the new fan coil unit piping.
Demolition in the 3rd and 4th Floor annex space continues.
LSUHSC Facility Services personnel continue installing locksets on the 5th and 6th Floors.
Dental
Campus Roof Replacement:
The roofing contractor continues to work on punch-list items and is applying sealant to newly installed umbrellas around the bases of the exhaust fan supports.
Dental Clinic Building Lab Renovations:
The electrical contractor continues removing old wiring and installing the new electrical rough-ins.
Dental School
Small Auditoriums:
The contractor is laying out the new walls and the concrete flooring for the auditoriums.
The electrical sub-contractor continues to remove the old electrical and telecommunications wiring.
Pipe insulation and old ductwork was removed this weekend.
Library
Commons:
LSUHSC electricians continue the rough in for new light switches.
Lions/LSU
Clinic Permanent Repairs and Mitigation:
Crews completed the installation of sheet rock in the 7th Floor laboratory.
The contractor is installing ductwork in the mechanical room on the S. Prieur/Gravier St. side of the 6th Floor.
The mechanical sub-contractor is piping in the VAVs on the 6th Floor, east side.
The electrical sub-contractor is running cable from the main Entergy vault to the new switchgear location on the 2nd Floor.
MEB
MDL #5:
The contractor continues relocating sprinkler heads in the ceiling.
They continue installing the new HVAC and return grilles in the grid.
The flooring sub-contractor began preparing the floor.
MEB 2nd
Floor Lobby Renovations:
The new sub-floor was poured over the weekend.
The contractor is hanging sheet rock on the walls by the Mens Bathroom.
MEB
4th Floor Ceiling Replacement:
Work continues on installing the new ceiling grid and relocating the sprinkler heads.
Residence
Hall 2nd Floor Lobby Expansion:
The newly fabricated steel has been delivered and the installation began today.