|
Tuesday, September 9, 2008
1542 TULANE:
-
General contractor continued demolition in the 3rd and 4th
floor annex.
-
Contractor completed formwork for the area way concrete
lids.
-
Facility Services continued installing new fan coil units
on the 6th floor. Work
continued on renovations to the 8th floor restroom, 6th floor restrooms and
various maintenance items throughout the building.
-
Security contractor continued running wire and preparing
for camera installation on the exterior doors.
-
Elevator contractor continues work on elevator #4.
DENTAL CAMPUS 6th and 8th FLOOR RENOVATIONS:
DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:
LIBRARY COMMONS:
LIONS BUILDING MITIGATION:
-
Mechanical subcontractor is running lines for new Med Gas
on 6th floor simulation rooms; running supply duct on the Gravier side of
the 6th floor; insulating heating hot water lines on the Bolivar/CSRB side
of 6th floor; insulating the supply duct following the installation on the
Gravier side of the floor; running waste line from 5th floor to new 6th
floor scrub sinks; installing
water closet carriers and demoing old pipe in bathrooms on the Bolivar side
of the 6th floor; and piping in sump pumps in the elevator pits 3 and 4.
-
Glass subcontractor is installing new metal trim pieces on
the 1st floor Gravier side.
-
Electrical subcontractor is tying in conduit for new
transfer switches on the 2nd floor in new electrical room on the CSRB side;
and moving electrical pipe and boxes out of the way of the new air
conditioning system on the 6th floor.
-
Iron subcontractor is setting anchors for new stairwell.
-
Contractor is painting 6th floor CSRB and Gravier side and
mudding on 7th floor.
MDL-5 LAB:
-
Contractor completed installation of VCT tiles.
-
Ceiling tiles installation completed in room 4106A, 4109,
4122A, and 4123A; contractor began work in main MDL room.
MEB 2nd FLOOR LOBBY:
MEB 4th FLOOR CEILING REPLACEMENT:
RESIDENCE HALL LOBBY EXPANSION:
|