Wednesday, September 10, 2008
1542 TULANE AVE.:
-
General contractor continued demolition in the 3rd and 4th
floor annex.
-
Contractor completed preparations for placing the area way
concrete lids.
-
New Orleans Sewerage and Water Board contractor repaired
sidewalk in the area of the new irrigation meter.
-
Elevator contractor continued work on elevator #4.
-
Facility Services continued installing new fan coil units
on the 6th floor. Work
continued on renovations to the 8th floor restroom and installation of
restroom accessories throughout the building.
Work commenced roughing in plumbing in the 7th floor lounge for the
new kitchenettes.
DENTAL CAMPUS 6th and 8th FLOOR RENOVATIONS:
DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:
LANDSCAPING & EXTERIOR WORK:
LIBRARY COMMONS:
LIONS BUILDING MITIGATION:
-
Mechanical subcontractor is running lines for new Med Gas
on the 6th floor simulation rooms; running supply duct on the Gravier side
of the 6th floor; insulating heating hot water lines on the Bolivar/CSRB
side of the 6th floor; raising existing waste lines below the new ceiling
height on the 6th floor; piping in waste lines and vents for water closet
carriers and urinals in the bathrooms on the Bolivar side of the 6th floor;
and piping in AHU in mechanical room on the 1st floor on the Gravier/Bolivar
side.
-
Glass subcontractor is installing new metal trim pieces on
the 1st floor CSRB side.
-
Electrical subcontractor is pulling wire to new panel
boxes in the new electrical room on the on the 2nd floor CSRB side.
-
Iron subcontractor laid out the steel beams for the first
2 floors of the new stairwell.
-
Contractor is mudding walls on 2nd floor new switchgear
room.
-
Contractor is preparing floor in bathrooms on the 1st
floor CSRB/Bolivar side.
MDL-5 LAB RENOVATION:
MEB 4th FLOOR CEILING REPLACEMENT:
RESIDENCE HALL LOBBY EXPANSION:
|