Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, September 16, 2008

 

1542 TULANE AVE.:

  • General contractor continued demolition in the 3rd floor annex.
  • General contractor placed new concrete decks in the lounges on 4th, 5th, 6th and 7th floors.
  • Elevator contractor continued work on elevator #4.
  • Lighting contractor continued installing new light fixtures in the 1st floor Family Medicine offices.
  • Painting contractor continued painting stairwell and hallway ceilings.
  • Security contractor installed the new pan-tilt-zoom camera for the front entry.
  • Contractor placed new concrete lids on the area ways in the front and rear of the building.
  • Facility Services continued installing new fan coil units in 615, 616, and 617. Preparations for installation of landscaping irrigation piping commenced in front of the building.

DENTAL CAMPUS ROOFING REPAIRS:

  • Roofing Contractor is repairing roof at wing walls of Clinic Building and is waterproofing perimeter of Clinic roof.

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • General Contractor continues to construct framing for ceiling in Auditorium B and is laying-out framing for ceiling in Auditorium A.

LANDSCAPING & EXTERIOR WORK:

  • Storm-toppled trees were replanted and stabilized in front of Resource Center and Lions Eye Center.

LIBRARY COMMONS:

  • Contractor framed the wall nearest to freight elevator.

LIONS BUILDING MITIGATION:

  • Mechanical subcontractor is running lines for new Med Gas on the 6th floor simulation rooms; running supply duct on Gravier side of 6th floor; insulating heating hot water lines on Bolivar/CSRB side of 6th floor; insulating supply duct on Gravier side of 6th floor; rerouting existing waste lines below new ceiling height on 6th floor; installing new waste lines from the 5th floor to the new 6th floor bathrooms on the Bolivar/CSRB side, and piping in the AHU in mechanical room on 1st floor on the Gravier/Bolivar side of the building.
  • Electrical subcontractor is terminating the wire to new panel boxes on the 2nd floor in new electrical room on the CSRB side; re-routing outlets around med gas lines by the 6th floor simulation rooms; and installing outlets in new lab area on the 7th floor.
  • Iron subcontractor is welding new stairwell beams on 2nd and 6th floors on the outside of the building on Gravier side.

MDL-5 LAB RENOVATION:

  • Contractor continues installing casework (unistrut frame), the LCD panels display, and reinstalling air, gas and vacuum line for new casework.
  • Contractor is installing new partition panels.

MEB 4th FLOOR CEILING REPLACEMENT:

  • Contractor began installing exit signs and continued installing ceiling tiles.

RECEPTION CENTER:

  • Fire Marshall Inspection is scheduled for Monday 9/22/2008 @ 2pm.

RESIDENCE HALL LOBBY EXPANSION:

  • The contractor removed the temporary ramps between tower A and tower B elevators and removed the bricks at all door entrances to make a clean transition for the new floor.