|
Wednesday, September 17, 2008
1542 TULANE AVE.:
-
General contractor continued demolition in the 3rd floor annex.
-
General contractor finished new concrete decks in the lounges on 4th,
5th, 6th and 7th floors and commenced wall construction.
-
Elevator contractor continued work on elevator #4.
-
Lighting contractor continued installing new light fixtures in the 1st
floor Family Medicine offices.
-
Painting contractor continued painting stairwell and hallway ceilings.
-
Security contractor installed the new cameras at the parking garage
entrance.
-
Contractor completed new concrete lids for the area ways in the front and rear
of the building.
-
Facility Services continued installing new fan coil units and painting in rooms
on the 6th floor.
DENTAL CAMPUS ROOFING REPAIRS:
-
Roofing Contractor is repairing roof decking on the elevator penthouse of
the Administration Building - a 10ft x 10ft section of roof decking,
insulation, mineral board, and roof cap sheets have been removed. The
Contractor installed sheet metal and concrete to repair the deck and is
re-installing the insulation, mineral board and cap sheets.
DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:
-
General Contractor has begun to construct the framing for the ceiling in
Auditorium A.
DENTAL CAMPUS 6TH AND 8TH FLOOR RENOVATIONS:
-
Mechanical Contractor is installing pipe hangers and preparing pipe fittings
for installation of vacuum piping in room 8405.
LANDSCAPING & EXTERIOR WORK:
-
Commenced installation of landscaping irrigation piping at 1542 Tulane.
LIONS BUILDING MITIGATION:
- Mechanical subcontractor is running lines for new Med Gas on the 6th
floor simulation rooms; running supply duct on Bolivar/Gravier side of 6th
floor; insulating heating hot water lines on Bolivar side of 6th floor;
insulating supply duct on Bolivar side of 6th floor; removing storm drains
in the way of the duct work on Gravier side of 6th floor; and piping in the
AHU in mechanical room on 1st floor on the Gravier/Bolivar side of the
building.
- Electrical subcontractor is installing outlets in new lab area on the
7th floor and running conduit to the new fire panel room on 2nd floor.
- Iron subcontractor was welding the new stair structure on the top of 1st
floor/bottom of 2nd floor; hanging steel for the new partitions on the 6th
floor Gravier side.
- Contractor is sealing penetrations on 7th floor; installing ceiling wire on 7th floor; and framing the bathroom on the 6th floor Bolivar / CSRB side.
MDL-5 LAB RENOVATION:
-
Contractor continues installing casework (unistrut frame) and LCD panels
display, and is reinstalling air, gas and vacuum line for new casework.
-
Contractor completed installing new partition panels, including new door and
frame, in room 4123A.
MEB 4th FLOOR CEILING REPLACEMENT:
- Contractor installed ceiling tiles and return grille on Roman St. side.
RESIDENCE HALL LOBBY EXPANSION:
- Contractor delivered materials and began setting up installation of
self-level concrete floor.
|