Friday, September 19, 2008
1542 TULANE AVE.:
-
General contractor continued demolition in the 3rd floor annex.
-
General contractor continued wall construction in the lounges on 6th and 7th floors.
-
Painting contractor continued painting stairwell and hallway ceilings.
-
Furniture vendor delivered new furniture for the University Police office on 1st floor.
-
Facility Services continued installing new fan coil units and painting in rooms on the 6th floor. Plumbers continued mechanical rough-in for the kitchenettes in the 6th floor lounge. Commenced clearing building supplies from the 1st floor auditorium.
DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:
-
General Contractor continues to construct the framing for the ceiling in Auditorium A.
-
Mechanical Contractor is setting-up for the chilled water pipe valve installations required for the new AHU.
DENTAL CAMPUS 6TH AND 8TH FLOOR RENOVATIONS:
-
Mechanical Contractor continues installing pipe hangers and vacuum piping for room 8405.
LIBRARY COMMONS:
-
Contractor installed cementitious board on the frieze wall.
LIONS BUILDING MITIGATION:
-
Mechanical subcontractor is running lines for new Med Gas on the 6th floor simulation rooms; insulating supply duct on CSRB side of 6th floor; piping in VAV’s on Gravier side of 6th floor; installing the vent line and the water lines to the water closets and the urinals on the 6th floor Bolivar/CSRB side bathroom; and piping in the AHU in mechanical room on 1st floor on the Gravier/Bolivar side of the building.
-
Iron subcontractor was rained out.
-
Contractor is sealing penetrations on 6th floor; hanging door frames on the CSRB side of 6th floor; and framing the bathroom on the 6th floor Bolivar / CSRB side.
MDL-5 LAB RENOVATION:
-
Contractor is installing countertop for the unistrut frame and connecting plumbing fixtures; continues installing speakers and mounting bracket for LCD TV; and completed installation of new partition panels.
MEB 4th FLOOR CEILING REPLACEMENT:
-
Contractor continued to install ceiling tiles on the South Roman side of the floor.
RESIDENCE HALL LOBBY EXPANSION:
-
Contractor completed shot blasting the 2nd floor from tower A to tower B elevator.
RESIDENCE HALL WALKWAY RESURFACING:
-
Contractor applied second underlayment layer for the walkway surface.
|