Wednesday, September 24, 2008

 

1542 TULANE AVE. :

  • Repairs to the ceiling in Room 718 have begun.
  • The construction of walls for the 4th Floor lounge continues. 
  • The painting contractor continued painting the restrooms.
  • The security contractor completed installation of access control for the front doors and the side doors closest to the District Energy garage.
  • LSUHSC Facility Services continued installing new fan coil units. 
  • Plumbers continued the mechanical rough-in for the kitchenettes in the lounge on the 4th Floor. 
  • Electricians are trouble-shooting electrical issues throughout the building.

 

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • The contractor continues to construct the framing for the ceiling in Auditorium A. 
  • The electrical subcontractor continues making preliminary rough-ins for new lighting in both Auditoriums.

 

DENTAL CAMPUS ROOFING REPLACEMENT:

  • The contractor finished installing new walk pads on the Clinic Building roof.

 

DENTAL CAMPUS 6th & 8th FLOOR LAB RENOVATIONS:

  • The mechanical subcontractor continues to install domestic water lines for Room 8401.

 

LANDSCAPING AND EXTERIOR WORK:

  • Crews continued installing landscaping irrigation in front of 1542 Tulane Ave.

 

LIBRARY COMMONS:

  • Contractor continues to frame the new wall nearest the passenger elevators.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The contractor is placing concrete on the floor of the new equipment area on 2nd Floor.
    • Ceiling grid is being installed on the 7th Floor.
    • They are prepping the floors for the new tile on the 7th Floor.
    • The floor penetrations on the CSRB side of the 6th Floor are being sealed.
    • A crew is laying out the CMU walls for the 1st Floor on the S. Prieur St. side.
    • Door frames are being hung on the S. Prieur St. side of the 1st Floor.
  • The mechanical subcontractor is braising joints in the new Med Gas lines serving the 6th Floor simulation rooms.
    • They are running supply duct on the Bolivar St. side of the 6th Floor by the lab.
    • The new supply duct on the CSRB/Bolivar St. side of the 6th Floor is being insulated.
    • The supply grills are being installed on the 7th Floor.
    • A crew is re-routing waste lines going to the 7th Floor in the 6th Floor ceiling that are in the way of the new duct work.
    • They are piping in the AHU in the mechanical room on the 1st Floor on the Gravier St./Bolivar St. side of the building.
  • The electrical subcontractor is installing electrical receptacles on the CSRB side of the 6th Floor.
    • They are pulling phone and data wire on the 7th Floor for the new lab.
  • The iron workers are decking the 2nd and 3rd Floor landings in the new exterior stair.
    • Crews are also installing the hand rails.
  • The fire sprinkler subcontractor was moving sprinkler heads on the 7th Floor.

 

MEB MDL-5 LAB RENOVATIONS:

  • The casework contractor is installing pedestal frames in the main MDL room.
  • The plumbing and electrical subs continue to reconnect plumbing fixtures and electrical outlets as they work behind the casework installers.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • Boe-Tel is installing data wires on the 2nd Floor for Room 2108.

 

MEB 4th FLOOR CEILING REPLACEMENT:

  • The contractor has completed framing the ceiling nearest the return air grilles and is installing new supply grilles.

 

RESIDENCE HALL LOBBY EXPANSION:

  • The flooring subcontractor is placing a second layer of mortar concrete from the S. Roman St. side of the building toward the Tower B elevator.
  • Crews continue installing wood blocking on the new roof of the addition.