The general contractor completed insulating the new walls in the lounges on the 3rd through the 7th Floors.
Crews continue the drywall ceiling repair in Room 718.
New suspended ceiling grid is being installed in the 7th and 8th Floor elevator lobbies.
The painting contractor continues painting offices on the 5th through the 8th Floors.
The electrical contractor continues installing new light fixtures in Conference Room 524.
The flooring contractor continues carpet repair and installation in rooms on the 7th Floor and floor tile installation in stairwells and the restroom alcoves.
LSUHSC Facility Services plumbers continue with the mechanical rough-in for the kitchenettes in the lounge on the 4th Floor.
Facility Services electricians installed power feed cables for the systems furniture in Room 551.
Crews are insulating the chilled water and hot water piping that feeds newly installed fan coil units on the 5th and 6th Floors.
The plumbing subcontractor installed drain lines on the fan coil units in Room 109E.
DENTAL
CAMPUS AUDITORIUMS A & B RENOVATIONS:
The 2nd coat of mastic moisture protection is being applied to the exterior walls in Auditorium A.
The electrical sub-contractor continues to install the lighting rough-ins for Auditorium A.
DENTAL
CAMPUS ROOF REPLACEMENT:
Needham Roofing continues to install walk pads on the Administration Building .
DENTAL
CAMPUS 6th & 8th FLOOR LAB RENOVATIONS:
The mechanical subcontractor tied-in the domestic hot and cold water lines into the building systems.
LIBRARY
COMMONS:
The contractor continues to frame the wall near the passenger elevator.
LSUHSC plumbers are running water lines for the coffee kiosk.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor is insulating the new supply duct on the 7th Floor.
They continue to re-rout waste lines from the 6th Floor to the new lab on the 7th Floor.
The heating hot water lines in the 6th floor simulation rooms are being rerouted.
A crew is running taps off of the main supply duct to the VAV boxes on the 6th Floor.
A leak test is being performed on the heating hot water lines on the Gravier St. side of the 6th Floor.
Supply duct is being run in the 1st Floor mechanical room on the Bolivar St./Gravier St. side of the building.
A crew is running drains for the AHU in 1st Floor mechanical room the Gravier St./Bolivar St. side of the building.
The electrical subcontractor is relocating conduit that would fall below the new ceiling line on the Gravier St. side of the 6th Floor.
New cable tray is being installed on the Gravier St. side of the 6th Floor.
A crew is relocating electrical wiring from a wall by the new stairwell on the 2nd Floor.The wall is being demolished to make room for a new fire wall.
The iron subcontractor is welding the front of the steel frame for the new exterior stairwell.
The sprinkler subcontractor continues relocating sprinkler heads on the 7th Floor.
The contractor is installing new ceiling grid on the CSRB side of the 6th Floor.
They are installing ceiling wire on the CSRB side of the 6th Floor.
New door frames are being hung on the CSRB side of the 6th Floor.
A crew is sealing wall penetrations on the 6th Floor.
The wall by the stairwell on the 2nd Floor is being demolished to install a new fire wall.
The installation of CMU walls on the 1st Floor on the S. Prieur St. side is progressing.
MEB MDL-5
LAB RENOVATION:
The casework subcontractor is installing epoxy sinks in the main MDL lab.
The plumbing sub continues to reconnecting air/gas/vac for the casework and acid waste drain for the sink cabinets in the main MDL lab.
MEB
2nd FLOOR LOBBY REMOVATIONS:
The contractor is capping off the top of the new store walls and installing sheetrock by the Mens bathroom