Repair of the ceiling grid in the front hallway on the 6th and 7th Floors is proceeding.
The contractor is sanding the lounge walls in preparation for primer and paint.
Drywall repairs in offices on the 3rd Floor continue.
The electrical contractor continues installing new light fixtures in conference rooms on the 6th Floor.
The furniture vendor finished the installation and arrangement of furniture in offices on the 7th Floor.
They placed furniture in the final arrangement in 80 percent of the offices on the 1st Floor.
LSUHSC Facility Services continues installing new paper towel and soap dispensers in restrooms on all floors.
They continued working on punch list items on the 5th Floor.
DENTAL CAMPUS AUDITORIUMS A & B
RENOVATIONS:
The general contractor framed up walls in Auditoriums A and B.
The electrical contractor installed junction boxes and mounted hardware for the light fixtures in both auditoriums.
DENTAL
CAMPUS 6th & 8th FLOOR LAB RENOVATIONS:
The mechanical contractor installed vacuum piping for Room 8405.
The general contractor removed thimbles from the demolished lab casework in Room 8405.
DENTAL SCHOOL
ROOF REPLACEMENT:
The contractor installed the final sheet metal vent caps on the Administration Building roof and finished installing roofing cap sheets over the marred roof sheets.
The contractor removed the dumpster and excess materials from the job site.
EXTERIOR/LANDSCAPING
WORK:
The new trash compactors installed around campus were put into operation.
Landscape grading continues in front of 1542 Tulane Avenue .
LIBRARY
COMMONS:
Contractor installed sheetrock in the elevator lobby and restroom.
The sprinkler contractor removed existing sprinkler piping that conflicted with the new ceiling layout.
LIONS
BUILDING MITIGATION
The mechanical subcontractor continued insulated supply duct on the 6th Floor, S. Prieur St. side of the building.
Crews are installing branch lines to the VAV boxes on the Gravier St./S. Prieur St. side of the 6th Floor.
They moved a vent line in the bathroom on the 6th Floor that conflicted with a duct.
The subcontractor trimmed out cabinets and a fume hood on the 7th Floor and welded the exhaust for the fume hood.
The electrical subcontractor moved the transformer on the S. Prieur St. side of the 2nd Floor.
The iron subcontractor welded the landings on the 4th Floor.
The sprinkler subcontractor installed sprinkler heads on the 6th Floor on the Gravier St. side of the building.
They relocated sprinkler heads on the 1st Floor on the S. Prieur St. side.
The casework subcontractor continued installing new lab casework on the 7th Floor.
Additional door frames were installed on the 6th Floor.
They re-waterproofed the elevator pit on the 1st Floor.
MEB MDL-5
LAB RENOVATIONS:
The casework contractor installed panels and countertops for the middle island in all 4 quadrants of the lab.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor continued to skim coat the pans of the honeycomb ceiling.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor constructed the concrete form for the storefront curb at the S. Roman St. side of the Residence Hall.