The general contractor completed the drywall ceiling installation in Room 718.
They continued installing new suspended ceiling grid in the 8th and 7th Floor elevator lobbies.
The walls in the 4th Floor lounge have been dry walled.
Crews continued installing walls in the 5th and 6th Floor lounges.
The painting contractor completed painting offices on the 8th Floor and continued painting offices on the 5th through 7th Floors.
The electrical contractor continues installing new recessed light fixtures in conference rooms on the 5th through the 7th Floors.
The flooring contractor continues carpet repair and installation in rooms on the 6th Floor and floor tile installation in stairwells and the restroom alcoves.
LSUHSC Facility Services completed installing irrigation piping in the front of the building.
They ran the electrical conduit for the new bollards (sidewalk lights).
DENTAL
CAMPUS AUDITORIUM A & B RENOVATIONS:
The electrical sub-contractor is installing whips and continues to install conduit rough-ins for the lighting in Auditorium A.
DENTAL
CAMPUS ROOF REPLACEMENT:
The contractor is repairing flashing and is caulking around the perimeter of the Clinic Building penthouse.
DENTAL
CAMPUS 6th & 8th FLOOR LAB RENOVATIONS:
The installation of gas lines for the peninsulas in Room 8405 is progressing.
Electrical sub-contractor is pulling wiring for the new electrical outlets.
LIBRARY
COMMONS:
The contractor is installing metal support tubes for the rollup fire door at the passenger elevators on the north side.
LSUHSC electricians are running conduit for the light fixtures near the center stairs.
LSUHSC plumbers continue to rough in the plumbing in the janitors closet.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical sub-contractor is insulating supply duct and heating hot water lines on the Gravier St. and the CSRB side of the 6th Floor.
They continue to pipe in the VAV on the 6th Floor and run supply duct in the 1st Floor mechanical room.
The electrical sub-contractor is installing electrical outlets on the new CMU walls on the 1st Floor and pulling new data wires on the 6th Floor.
Iron sub-contractor is welding the taps on the steel structure on the 3rd and 4th Floors for the new stairwell.
They are installing the supports for the removable wall panels in the large lecture room.
The sprinkler sub-contractor is relocating sprinkler heads on the Gravier St. side of the 6th Floor.
The contractor is installing floor tiles on the 7th Floor in the small rooms of the new lab.
The ceiling grid on the CSRB side of the 6th Floor is being hung.
A crew is installing ceiling wire on the CSRB side of the 6th Floor.
They continue hanging door frames on the CSRB side of the 6th Floor.
A crew is sealing wall penetrations on the Gravier St. side of the 6th Floor.
Sheetrock is being hung by the simulation rooms on the 6th Floor.
CMU walls are being constructed on the 1st Floor on the S. Prieur St. side of the building.
MEB MDL-5
LAB RENOVATIONS:
The plumbing sub-contractor completed reconnecting acid waste drain lines for the epoxy sinks in the main MDL room.
They continue to rough-in the plumbing in Room 4109 for the nine stainless steel sinks.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor is framing the fur down between the lecture halls.