The general contractor continued drywall repairs in offices on the 2nd and 3rd Floors.
They installed suspended ceiling grid in the lounges on the 6th and 7th Floors and started installation of ceiling grid in the lounges on the 4th and 5th Floors.
The electrical contractor continued installing new light fixtures in hallways and stairwells.
The furniture vendor continued arranging furniture in offices on the 5th Floor.
The construction cleaning contractor shampooed the 7th Floor office carpets.
They continued cleaning on the 7th and 6th Floors.
Crews returned to cleaned areas that failed inspection on the 8th Floor.
Facility Services continued to work on punch list items on floors 5 to 8.
DENTAL
CAMPUS AUDITORIUMS A & B RENOVATIONS:
The general contractor installed wood supports for the baseboards in Auditorium A along the south wall and installed insulation on the east and south walls of Auditorium A.
The electrical contractor installed wiring and conduit for the walls in Auditorium A.
The contractor installed metal framing for the soffit and ceiling in Auditorium B.
DENTAL
CAMPUS 6th & 8th FLOOR LAB RENOVATIONS:
The mechanical contractor installed horizontal gas and vacuum piping inside the interior walls of the tissue culture room in Room 8405J.
They installed the drain line for the fume hood in Room 6335.
The general contractor removed the door and frame at the south entrance of Room 8405.
They framed the exterior wall for Room 8405K and the south entrance of Room 8405.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor installed three sinks and faucets in the 7th Floor lab.
The plumbers continued to rough in the waste, vent, and domestic water lines for the urinals and the toilets in the bathroom on the 1st Floor.
The iron subcontractor welded the decking for the roof and saddles on the 4th and 6th Floor.
The casework subcontractor installed four base cabinets and six countertops in the 7th Floor lab space.
The contractor installed additional fur downs on the 6th Floor.
They continued to tape and float the fur downs on the CSRB side of the 6th Floor.
A crew installed tile floor at the entry way of the new lab on the 7th Floor.
MEB MDL-5
LAB RENOVATIONS:
The contractor installed electrical receptacles for the pedestal frames in the MDL room.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor installed ceiling grid on the Roman St. side of the lobby.
The mechanical subcontractor removed the existing supply and return air ductwork.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor grouted the new tiles that have been laid between the A and B Towers.