The general contractor continued drywall repairs in offices on the 2nd and 3rd Floors.
Crews completed installing the suspended ceiling grid in the lounges on Floors 4 to 7.
The electrical contractor continued installing new light fixtures in hallways and stairwells.
The construction cleaning contractor continued cleaning on the 7th and 6th Floor and continued rework in the areas that failed inspection on the 8th Floor.
LSUHSC Facility Services continued to work on punch list items on Floors 5 to 8.
They demolished the temporary loading dock ramp in the parking garage driveway.
DENTAL
CAMPUS AUDITORIUMS A & B RENOVATIONS:
The general contractor installed insulation on the west and north walls of Auditorium A and installed new sheetrock on all walls in Auditorium A.
The electrical contractor installed wiring and conduit for Auditorium B.
The insulation contractor installed insulation in the block walls and ceiling of the mechanical room.
DENTAL
CAMPUS 6th & 8th FLOOR LAB RENOVATIONS:
The insulation contractor installed pipe insulation on the water lines above the ceiling in Room 7407 and the simulation lab.
The general contractor framed the new door openings.
The contractor framed the exterior wall on the north side of Room 8405.
The mechanical contractor tied-in the new vacuum, gas, hot water, and cold water lines for Room 6335.
They removed the old ice water, de-ionized water, and steam lines in Rooms 6335 and 6333.
EXTERIOR/LANDSCAPING:
The landscapers continued grading the front lawn of 1542 Tulane Avenue .
LIBRARY
COMMONS:
The contractor installed fire sprinklers in the multi-media rooms.
LIONS
/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor installed two sinks and faucets in the 7th Floor lab.
They installed five air and gas turrets in the 7th Floor lab.
Crews insulated the heating hot water lines and supply duct on the 6th Floor on the S. Prieur St. side of the floor.
They roughed in the waste and vent lines for the urinals and the water closets in the bathroom on the 1st Floor, Bolivar St. side.
The iron subcontractor welded the exterior stairwell saddles on the 1st, 4th, 5th, and 6th Floors.
They finished the last welds on the roof decking and finished welding the stairs on the 3rd level.
The casework subcontractor installed 3 shelving units, 3 cabinets, and 4 counters in the 7th Floor laboratory.
The electrical subcontractor installed lights on the 6th Floor, CSRB side and also in the 2nd Floor build out area.
The sprinkler subcontractor installed sprinkler heads on the 2nd Floor in the new build out area.
The contractor installed door hardware on the 7th Floor.
They installed glass in the new door frames on the 6th Floor, CSRB side.
A crew installed CMU on the 1st Floor on the Gravier St. side of the hallway closest to the CSRB.