The general contractor continued installing the new suspended ceiling grid and tiles in the 8th and 7th Floor elevator lobbies.
They completed installing sheetrock walls in the lounges on the 5th, 6th and 7th Floors.
The painting contractor continued painting offices on Floors 5 through 7.
The electrical contractor continued installing new recessed light fixtures in conference rooms on Floors 5 through 7.
They began laying out the pendant fixtures.
The flooring contractor continues carpet repair and installation in rooms on the 6th Floor and the installation of floor tile in stairwells and the restroom alcoves.
LSUHSC Facility Services personnel drilled through the planter base on the front porch to route new water and electrical service for the landscape irrigation.
The Print Shop equipment was moved into the old C Store for storage.
DENTAL
CAMPUS AUDITORIUM A & B RENOVATIONS:
Work was suspended today to accommodate the Alumni Event held in an adjacent lobby.
DENTAL
CAMPUS ROOF REPLACEMENT:
Needham Roofing is repairing flashing and caulking around the perimeter of the Administration Building penthouse.
LIBRARY
COMMONS:
The contractor installed door headers for the wall nearest the elevators.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor is insulating supply ducts and heating hot water lines on the S. Prieur St. side of the 6th Floor.
They are piping in the VAV on the 6th Floor in the simulation rooms.
A crew is installing the drain line for the floor on the 2nd Floor.
They are laying out the pipe for the pipe fabrication for the med air and gas on the 2nd Floor.
A crew is laying out the equipment pads for the med air and gas on the 2nd Floor.
The iron sub-contractor is welding the taps on the steel structure on Floors 3– 4 for the new stairwell.
The supports for the removable wall panels in the large lecture room are being installed.
The sprinkler heads on the Gravier St. and CSRB side of the 6th Floor are being relocated.
The contractor is installing ceiling grid on the CSRB side of the 6th Floor.
One crew is installing ceiling wire on the CSRB side of the 6th Floor.
Another crew is sealing wall penetrations on the Gravier St. side of the 6th Floor.
New sheetrock is being installed on walls by the simulation rooms on the 6th Floor.
They began demolishing the stairwell wall to prepare for the CMU wall installation on the S. Prieur St. side of the building.
The contractor is prepping for the plaster on the CSRB side of the 1st Floor.
They continue with the installation of the CMU walls on the 1st Floor on the S. Prieur St. side of the building.
MEB MDL-5
LAB RENOVATIONS:
The plumbing sub-contractor is connecting the medical air/gas/vac lines for the new turrets (valves) in the main MDL room and in Room 4109.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor is framing the ceiling by the Medical Center Stores space and framing the back of the columns in the storage areas.