The general contractor continued making drywall repairs in offices on the 3rd and 5th Floors.
The electrical contractor completed the installation of new light fixtures in the lounge on 7th Floor.
The electrical contractor continued installing new light fixtures in the 5th, 6th and 7th Floor conference rooms.
The construction cleaning contractor continued cleaning on the 6th Floor and began cleaning on the 5th Floor.
LSUHSC Facility Services painted Conference Rooms 728 and 729.
DENTAL
CAMPUS AUDITORIUMS A & B RENOVATIONS:
The general contractor installed wood blocking for the handrails and baseboard in Auditorium B.
The electrical subcontractor installed conduit for the lighting homeruns in Auditorium A and mounted the electrical panel in Auditorium B.
The general contractor installed framing for the ceiling in Auditorium B.
DENTAL
CAMPUS 6th & 8th FLOOR LAB RENOVATIONS
The mechanical subcontractor pressure tested the vacuum, air, and de-ionized water piping in Suite 8405 .
The general contractor framed the exterior north walls.
EXTERIOR/LANDSCAPING:
Facility Services completed installing the backflow preventer for the landscaping in front of 1542 Tulane Ave. and continued planting shrubs.
LIBRARY
COMMONS:
The contractor removed the fire alarm conduit from above the roll up door location.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor installed p-trap and drain line connections for all sinks and the fume hood in the 7th Floor lab.
They installed filler panels for the fume hood and adjacent cabinets and cleaned and wiped down all lab countertops and cabinets.
The contractor welded window wall clips and handrails from the 4th Floor to the 2nd Floor and installed the sub-floor for the Mens and Womens restrooms on the Bolivar St . Side of the 6th Floor.
The contractor erected four courses of block wall for the Womens restroom on the 1st Floor.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor removed ductwork from the lobby in the southwest corner.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor installed the metal framing for the new mailboxes.