Louisiana State University Health Sciences Center Administration & Finance
 

Monday, November 17, 2008

 

1542 TULANE AVE. :

  • The general contractor continued work on the floor of Room 545.
  • Preparations continue for installation of the new light fixtures in the 1st Floor lobby.
  • The construction cleaning contractor continued cleaning restrooms on the 1st Floor and offices that have failed inspection on the 5th Floor.
  • The network wiring contractor ran new data wire in the 7th and 8th Floor offices.
  • Facility Services continued making minor repairs on various floors. 

 

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • The general contractor installed foam supports and anchors for the riser seating in Auditorium B.
    • They installed additional sheetrock for the ceiling troughs in Auditorium A (1 trough remaining).
  • The electrical contractor installed additional wiring for the emergency lights in Auditoriums A & B.
    • Crews installed wiring for the step lighting in Auditorium B. 

 

DENTAL SCHOOL 6th & 8th FLOOR LAB RENOVATIONS:

  • The general contractor removed wood blocking from the east exterior wall in Room 8405.

 

LIBRARY COMMONS:

  • The mechanical contractor installed hard duct for the window ceiling grid. 

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The contractor installed 8 of 32 new switchgear feeders.
  • The mechanical subcontractor insulated duct on the 6th Floor.
  • The contractor welded the granite support corners on the outside stairwell.
  • The contractor installed restroom tiles on the west side of the 6th Floor.