The general contractor continued work on the floor of Room 545.
Preparations continue for installation of the new light fixtures in the 1st Floor lobby.
The electrical contractor continued installing new light fixtures in the front hallway on the 7th Floor.
The construction cleaning contractor continued cleaning restrooms on all floors.
All offices on Floors 1, 5, 6, 7 and 8 are complete.
The network wiring contractor completed new data wiring on the 7th Floor.
They continued running new wire on the 6th Floor.
The window glass contractor replaced broken windows on the 1st and 2nd Floor.
LSUHSC Facility Services continued making minor repairs on various floors.
DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:
The general contractor finished installing the forms and supports for the riser seating in Auditorium B.
The electrical contractor connected additional wiring for the lighting switch legs in Auditorium A.
The mechanical contractor assembled the AHUs, and set them on equipment pads.
ELEVATOR UPGRADES:
The contractor installed new carpet for Elevator 3 & 4 in the Resource Center .
EXTERIOR/LANDSCAPING:
LSUHSC Facility Services installed sod in front of 1542 Tulane Avenue .
DENTAL SCHOOL 6th & 8th
FLOOR LAB RENOVATIONS:
The general contractor removed wood blocking from the north exterior wall in room 8405.
LIBRARY COMMONS:
The contractor installed the ceiling grid in the multimedia room.
LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor finished backfilling the storm drain.
A crew insulated chill and heating hot water lines on the east side of the 1st Floor.
Pipe was installed for the new medical air and vacuum on the 2nd Floor.
They demolished the existing medical gas pipe on the east side of the 2nd Floor.
The domestic cold water valve for the 6th Floor simulation room was relocated.
The exhaust lines for the med gas bottle room on the 6th Floor were installed.
The electrical subcontractor installed eight feeders for the new switchgear.
They installed the cable tray feeders on the south side of the 1st Floor.
The iron subcontractor welded the granite curtain wall brackets on the northwest side of the 1st Floor.
The glass subcontractor caulked the exterior window frames on the south side of the 1st Floor.
They installed the interior window trim on the 1st Floor at the entrance and on the south side of the building.
The fireproofing subcontractor primed welds on Floors 1 through 3 of the exterior stair tower.
The contractor stripped and waxed the floor of the 7th Floor lab.
They installed restroom wall tiles on the west side of the 6th Floor.
The marker board locations on the south side of the 6th Floor were painted.
Crews installed sheetrock around the recessed television monitor locations on the north side of the 6th Floor.
They installed CMU on the southeast corner of the 1st Floor.
RESIDENCE HALL LOBBY EXPANSION:
The contractor installed sheetrock for a temporary wall,which will remain in place while the old curtain wall is removed and the new curtain wall is installed.
The contractor removed existing 2x4 light fixtures and wall mount light fixtures on the mezzanine level between the A & B towers.